System Benefits Charge IV (SBCIV) Timeline

Technology and Market Development Program Plan Development Milestones

  • December 31, 2010 - Public Service Commission (PSC) order issued
  • January 17 - March 11, 2011 - Stakeholder/Constituency Outreach Meetings
  • By March 16, 2011 - Issue Draft Abbreviated Plan
  • Week of March 21, 2011 - Conduct Technical Conference
  • April 1, 2011 - Comments due
  • April 1 - May 1, 2011 - NYSERDA develops Operating Plan
  • May 1, 2011 - Operating Plan submitted to PSC
  • Post May 1, 2011 - PSC comment and reply